Palm Jebel Ali
According to our internal inspection conducted on 10 March 2026, the project stands at 27.71% progress for Frond K, 24.71% for Frond L, 22.10% for Frond M, 29.20% for Frond N, 37.44% for Frond O, and 20.50% for Frond P.
The Real Estate Regulatory Agency reports progress at 25.11% for Frond K, 24.71% for Frond L, 19.73% for Frond M, 24.20% for Frond N, 31.45% for Frond O, and 15.60% for Frond P, based on their inspections conducted on 27 January 2026.